Quantcast
Channel: Primavera Online Interaction » MSP
Viewing all articles
Browse latest Browse all 20

prim33105:Can I import MSP summary activities as WBS levels?

$
0
0
Solution ID: prim33105
Can I import MSP summary activities as WBS levels?
Status: Reviewed
Version(s): 5.0



Problem: Can I import MSP summary activities as WBS levels?
Problem: Can I choose how MSP summary activities are imported?
Problem: Why are MSP summary activities imported as activities in 5.0?
Problem: When importing from Microsoft Project, is there a way to prevent the creation of WBS Summary activities for each level of the WBS?
Problem:

Restore summary task / WBS option in MPP import template to have ability to choose whether or not a Microsoft Project import will create WBS Summary activities.

Cause: In 5.0, ‘Summary Activities’ from MS Project are imported as ‘WBS summary’ activities.  This is to ensure that data such as relationships and code assignments on the MSP summary activity is not lost.

The option to import the summary activities as WBS levels is no longer included in Project Management 5.0.

Fix: This issue is an existing Enhancement Request.

Viewing all articles
Browse latest Browse all 20

Trending Articles