Solution ID: prim20163 |
Application event when importing an MPP project: Event Code: FVRVE-1992-6" |
Status: Reviewed |
Version(s): 3.5.1, 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 |
Problem: | Application event when importing an MPP project:Event Code: FVRVE-1992-6 Message: Field value required. validation error for column COST_LOAD_TYPE, value “*** null ***” |
Problem: | Full Exception report: ***************************************************** Executable: PM.exe Detail: 2: validation error for column COST_LOAD_TYPE, value “*** null ***” |
Cause: | This issue is caused by having ‘blank rows’ in the schedule in MS Project as shown in the screen shot below: Image may be NSFW. The ‘COST_LOAD_TYPE’ field in Primavera Project Manager / Project Management is equivalent to MS Projects’ ‘Fixed Cost Accrual’ field. This determines how the cost is spread over the activity. Valid values are ‘Start’, ‘Prorated’ and ‘End’ which are equivalent to Primavera’s ‘Accrual Type’ values of: ‘Start of Activity’, ‘Uniform over Activity’ and ‘Finish of Activity’. Project Manager / Project Management is attempting to import the ‘Fixed Accrual Type’ as a blank row – which is not permitted. |
Fix: | To rectify the issue:
|